Judge upholds state approval of Superior gas plant; $700M project faces additional hurdles


Judge upholds state approval of Superior gas plant; $700M project faces additional hurdles


Efforts to halt construction of a natural gas generator in Superior suffered a setback Tuesday, though the $700 million project faces additional legal hurdles.

Dane County Circuit Judge Jacob Frost said utility regulators followed the law when they approved the Nemadji Trail Energy Center.

Frost rejected arguments made by the Sierra Club and Clean Wisconsin that the Public Service Commission failed to consider the full environmental impact of the plant, which would be jointly owned by Dairyland Power Cooperative and two Minnesota utilities...